One of the most unfortunate parts of the debate on the Caltrain/HSR project on the Peninsula is the lack of accurate information. NIMBYs and other project opponents have already convinced many people that an above-grade solution would be a sort of "Berlin Wall" through the city, and Jim McFall's video reinforces that errant conclusion. The problem is that McFall's video has been the only attempt to visualize what the corridor would look like with above-grade tracks.

Until now.

Mike, who brought us the point by point refutation of the notorious Cox-Vranich HSR denier report last year, is back to inject some sense and fact into the debate over HSR. He has put together a YouTube video of simulations of the Churchill Avenue crossing in Palo Alto - including the existing at-grade model, the proposed CHSRA above-grade solution, and the flawed McFall model. Mike added authentic sounds of the crossing - a recording of Caltrain crossing at-grade, and of the Acela. Here's the video:



You can see clearly that McFall's model is misleading on several counts. He has the dimensions all wrong - the structure is higher in McFall's model than is actually proposed, and the catenary poles are too densely packed together. More importantly, McFall's video doesn't include existing landscaping that would mitigate much of the visual impact of an above-grade solution. There are no trees in the McFall video, whereas Mike's video makes clear that trees are indeed part of the solution.

The results of misleading misinformation on the Caltrain/HSR project (such as the McFall video) could be seen in Atherton on Thursday night, where a crowd came to speak in favor of the city's avowed "tunnel or nothing" stance:

Duncan Jones, Atherton's public works director, laid out the town's case for both joining the lawsuit and still participating in the high-speed rail planning process. "We need to hedge our bets," he said.

Mr. Jones, a former rail consultant, said that the town's fallback position -- if the route doesn't change, put the high-speed trains in a tunnel, rather than on a raised berm -- isn't as far-fetched as it sounds.

The rail corridor in Atherton is lined by expensive homes, and widening it to accommodate high-speed rail would require purchasing swaths of private property.

"When (the authority) looks at all of the costs and impacts, they may find out that going underground may be cheaper," Mr. Jones said.

Jones's comments are barely credible. I cannot imagine that buying a few strips of backyard will cost a billion dollars - which would be the minimum estimate for tunneling through Atherton, even with a cut and cover model. The San Jose Mercury News article on the meeting noted that Hatch Mott MacDonald executives estimated a tunnel through Atherton would cost:

A tunnel on the Peninsula would likely follow the same model as the San Jose BART extension, Townsend said, because both areas have soft ground. A high-speed rail tunnel would likely cost somewhere between $100 million to $250 million per mile, compared to less than $100 million for an at-grade system, he said.

I have a difficult time imagining that the cost of eminent domain for a few backyards would be $100 million. I am also skeptical of the lowball cost of an HSR tunnel that Townsend offered, but even if these estimates are accurate, it represents a doubling of the cost of building on the Peninsula.

Such is the fact-free nature of the debate on the Peninsula, unfortunately. Let's hope Mike's more accurate animation gets spread far and wide, and that people on the Peninsula can actually make informed choices about the Caltrain/HSR project.

Friday, May 29, 2009

Review of Yesterday's FRA Meeting in Sacramento

NOTE: We've moved! Visit us at the California High Speed Rail Blog.

Thanks to Matt Melzer for attending and compiling these notes (with help from Ryan Stern) from yesterday's FRA meeting in Sacramento on high speed rail. Lots to chew over here! -Robert

Besides presentations from the feds, there was one from Amtrak's VP Policy and Development, Stephen Gardner, who emphasized that Amtrak wants to be THE national HSR operator. He also said that expanding state partnerships is "Amtrak's future."

Will Kempton, Mehdi Morshed, and Bill Bronte acted as the regional presenters, making the public case for California to receive stimulus funds based on the obvious success and maturity of California's passenger rail programs. Their PowerPoint also had nice maps showing CAHSR integrated with each existing Amtrak California corridor, as well as all three. Yet, there was no illustration of long-distance routes, regional rail systems, or Thruway motorcoach connections. So the visualization severely minimized the true reach of the state passenger rail network.

The Surfliner route north of LA looked like an errant finger, with San Luis Obispo positively orphaned. This, of course, has no relation to reality, with the existing Thruway connections to Hanford and the Bay Area, as well as the Coast Starlight and the future Coast Daylight. It's this lack of emphasis on statewide connections on the part of the HSRA that leads to situations like Pete Rodgers of SLOCOG opposing Prop 1A supposedly because he didn't think there was anything in it for SLO. Even if the $950 million for feeder rail and transit improvements didn't exist, he'd still be wrong.

After their presentation giving an overview of the federal HSR Strategic Plan and Next Steps (to which I'll refer readers to previous posts regarding details), Karen Rae (FRA Deputy Administrator), Paul Nissenbaum (FRA Director, Office of Passenger and Freight Programs) and Gardner engaged in Q&A. Some of the juicier questions:

Representative of LA County MTA: With the billions of dollars LA County voters approved for new transit projects in Measure R, why can't MTA use future HSR connectivity benefits as part of cost-effectiveness calculations for FTA New Starts applications? Why aren't FTA's criteria more holistic?

Rae: "We've talked more with FTA in the past 6 months than [we probably did] in the past 15 years." FRA and FTA are aware of such issues and will discuss them more moving forward.

Jason Lee, San Francisco MTA: With so much focus on cost, won't HSR grant applicants cut corners and shy away from key projects like the $1 billion Transbay extension?

Rae: We're "struggling" with how to handle such megaprojects, of which there are many across all modes, that demand huge resources concentrated in very small project areas. Some of these issues could be addressed in the transportation reauthorization bill. Criteria for numerous federal transportation grant programs could conceivably evolve.

Representative of International Brotherhood of Electrical Workers: Union Pacific is grappling with Positive Train Control, which system is best, and how to implement it. Shouldn't the feds lead the charge for one interconnected PTC system?

Rae: FRA and the Rail Safety Advisory Committee are working to support the federally-mandated effort for a national PTC standard. We hope that PTC will be as interoperable as other standard railroad equipment.

Gardner: Interoperability is in the law (S.294, the Passenger Rail Investment and Improvement Act [PRIIA], the Amtrak/passenger rail reauthorization and rail safety bill that passed last year). Train control will be a critical issue as we develop corridors that exceed 79 mph.

IBEW Rep.: UP gave the impression that they didn't know about the interoperability requirement!

Paul Dyson, President, Rail Passenger Association of California and SW Division Leader, National Association of Railroad Passengers [Disclaimer: I, Matt, serve under Paul on the NARP Council]: There's a lot of talk of partnerships today. Look at the three providers of passenger rail in Southern California: Amtrak, Metrolink, and Coaster are crummy partners [along the Surfliner route], with passenger-unfriendly schedule coordination. Who's to say states like Arizona or Nevada would ever be willing to work with California as regional "partners" in HSR development, as FRA is encouraging states within regions to do?

Rae: "It is not an easy conversation." But there's nothing like competitive grants to provide an impetus for partnership. "There's not nearly enough money to go around," but best practices in multi-state compacts will emerge from this process.

Representative of Brotherhood of Railroad Signalmen: Amtrak is mandated to be profitable; will HSR operations be?

Nissenbaum: Capital subsidies will be required, but it's the responsibility of applicants to account for operating expenses. Amtrak or other operators will seek assurances so that they're not exposed to any risk of operating losses.

Gardner: The profitability clause is gone from Amtrak's mission due to PRIIA, which did stipulate that Amtrak must still minimize the need for federal coverage of their operating losses. States must also cover the losses of any new services.

Rich Tolmach of California Rail Foundation (and plaintiff in the lawsuit seeking to invalidate CHSRA's EIR): Will the same FRA safety standards still apply to new high-speed equipment?

Nissenbaum: Absolutely, yes. We will need to create new standards for equipment that operates about 150 mph, since they don't currently exist.

Rae: FRA Administrator Joe Szabo isn't here today because he's touring European HSR equipment, seeing how they achieve both efficiency and safety.

Ryan Stern, State Representative, National Association of Railroad Passengers: Given the moribund state of the domestic passenger rail supply industry, how do we create an environment that allows for ongoing production of rolling stock, so that cars can be purchased quickly and affordably?

Gardner: This falls under the work of the PRIIA-mandated Next Generation Corridor Equipment Pool Committee [which is developing national standards for various types of passenger rail cars]. But we do have to live in the world we have now.

Rae: The White House is in active talks with our domestic industrial manufacturers to retool underutilized production capacity.

Matthew George, Caltrans: Do Amtrak's agreements with host railroads provide for HSR?

Gardner: They apply at any speed, hypothetically. But we'll work collaboratively with our partners and not just "show up" with high-speed passenger trains intermingling with slow freights.

George: How much can you rely on those agreements?

Nissenbaum: You can't; there must be operational agreements specific to each service. But "master agreements" can be a starting point.

Beverly Mason, AECOM: What is FRA's policy on adapting European and Asian HSR trains to domestic use?

Rae: "We will not compromise our safety record." But new technologies are being explored. Sealed HSR systems especially could support more exotic equipment.

Lastly, there was one hour of breakout groups to address the following three sets of questions, which we randomly called upon share with the whole audience at the end. At least a good 60 percent of attendees stayed for this, whereas crowds had apparently thinned considerably in other cities' workshops. Rae emphasized that FRA is taking all feedback seriously, since the entire national HSR effort is a nascent work-in-progress. The questions were:

1. What does success from a national perspective look like in 2 years, 5 years, and 10 years? How do we measure success?

2. What factors are critical for implementation of the program? What is the role of the federal government, states, and others?

3. What does your region need to succeed, in the short or long run?

All groups wrote their ideas on worksheets, which were ultimately collected. The FRA is expected to make the presentations given at the meeting available on the web "at some point in the future."

-Matt Melzer

Thursday, May 28, 2009

New Blog Layout

NOTE: We've moved! Visit us at the California High Speed Rail Blog.

by Rafael

Robert Cruickshank and I have decided to fiddle with the blog layout in an effort to improve its user-friendliness.


  • The text field for posts and comments is now wider, but anyone with a monitor resolution at least 1024 pixels wide should still be able to view the entire page without having to scroll horizontally.

  • We've reduced the number of recent posts on the blog's home page from seven to three to improve download times, especially when a recent post includes multimedia elements, e.g. Google Maps or Youtube videos.

  • The Blog Archive was moved up to the top of the sidebar on the right. Only the top level, i.e. the years, are shown by default to avoid pushing everything else down too far. To view older posts, please click on the little triangles to open and close the hierarchical index.

  • Just below it, we've added the new search widget Blogger has kindly made available.

  • For those would like to become a follower of this blog, we've added the widget for that at the very bottom of the sidebar. There's a choice to follow publicly or privately and you can stop following at any time. Followers will be notified of new posts on their Blogger dashboard.

Header Image

  • We would quite like to use a suitable background drawing or photo for a new header that is not subject to copyright or made available to us by permission.

  • The preferred dimensions are 920-960 pixels wide by 80-120 pixels high. A drawing should be in GIF, a photo in JPEG format with 50-80% quality to keep the file small.

  • The text "California High Speed Rail Blog" has to be prominently superimposed on the image, either in a suitable application or else using Blogger itself. The subtitle presently in the header will probably end up below the image or else be removed altogether.

  • A drawing could feature the blue-yellow-white color scheme adopted by CHSRA but not echo the Authority's logo - this blog has no official affiliation with that state planning body.

  • Neither photo nor drawing should include the logo of any railroad operator, foreign or domestic, nor should any train shown be clearly recognizable as a product of any particular train vendor.

We'll keep looking for appropriate options, but if you have a good image that meets the above criteria, that would be very welcome indeed. Please send it via email to Robert Cruickshank at his last name dot gmail dot com no later than June 15, 2009.

If we end up with multiple good candidates, we'll publish a post later this month with a poll so the readership tell us which they would prefer. Since internet polls are easily skewed (or skewered, Stephen Colbert-style), we'd also take the comments into considerations. In any event, due credit will be given to the creator of any contributed header image that appears on this blog.

Meanwhile, we'd appreciate your feedback on the changes we've made so far.

Wednesday, May 27, 2009

Two Thursday Meetings

NOTE: We've moved! Visit us at the California High Speed Rail Blog.

Tomorrow, Thursday May 28th, will see two meetings on the high speed rail project. I can't attend either of them, but hopefully you can!

First up is an FRA meeting in Rancho Cordova (Sacramento suburb) from 1PM to 4:30PM:

FRA’s High-Speed Intercity Passenger Rail Workshops
Start May 20, To Tour Nation

Dear Stakeholders:

As we begin to implement President Obama’s vision for developing a cohesive national intercity and high-speed passenger rail network. This vision was set forth in FRA’s Strategic Plan for High-Speed Rail (HSR) announced by President Obama, Vice President Biden, and U.S. Transportation Secretary LaHood, and sent to Congress that same day on April 16, 2009.

The workshops will be led by FRA Deputy Administrator Karen Rae or myself. Through these workshops, FRA is reaching out to the rail community in seven regions across the country to seek your input on the Interim Guidance we are required to issue on or before June 17, 2009, for the $8 billion in grant funds provided by the American Recovery and Reinvestment Act of 2009 (ARRA) for the high-speed rail corridors program, intercity passenger rail grants, and congestion grants. The workshops will enable FRA to discuss the HSR Strategic Plan with key stakeholders such as state departments of transportation, regional planning authorities, metropolitan leaders, associations and labor groups (under the ARRA, these workshops exclude the participation of lobbyists).

We seek your input not only to provide us with your regional vision of high-speed and intercity rail networks, but to enable stakeholders to focus on the critical factors that will make this program a success for generations to come.

The goal of the workshop is to take the first steps toward determining how we can best partner together to make the Strategic Plan a reality. During the workshop, you will have an opportunity to share experiences, raise concerns, provide insights, and make recommendations on several key issues and questions, as well as hear those of your colleagues and representatives from a regional perspective. The workshop schedule will include the following:

Introduction 10 minutes
Overview of FRA strategic plan and next steps 30 minutes
Amtrak presentation 15 minutes
Q & A 35 minutes
Regional presentation 30 minutes
Break 15 minutes
Working group break-out 1 hour
Wrap-up 15 minutes

The workshops will be held 1:00 p.m. 4:30 p.m. on the following dates and locations:

California Corridor: Sacramento May 28; Sacramento Marriott Rancho Cordova, 11211 Point East Drive, Rancho Cordova, CA 95742

In addition to participating in the workshop, I am inviting you and other members of the public to submit written comments to FRA by June 5, 2009, on issues that should be addressed in the Interim Guidance and specific recommendations on the criteria to be used in evaluating grant applications. FRA has created a public docket (Docket No. FRA-2009-0045) for the receipt of written comments. Please visit FRA’s Web site at: www.fra.dot.gov/us/content/2236 for information regarding the various ways in which you may submit comments to the public docket.

Please note, additional sessions to aid states with the mechanics of applying for ARRA funds will be scheduled after these workshops, as will informational sessions for industry, labor, intergovernmental and other interested parties.

I look forward to working with you over the coming months to ensure the grant programs funded by ARRA are implemented successfully.

Sincerely,
Joseph C. Szabo
Administrator
The Federal Railroad Administration

The other meeting is in Atherton at 7PM:

The meeting is open to the public, and will be held at the Jennings Pavilion in Holbrook-Palmer Park, 150 Watkins Ave. in Atherton.
Atherton officials, and many of the town's residents, have grave worries about the local effects of the state plan to run high-speed trains along the Caltrain corridor that bisects the town. If the high-speed rail line can't be rerouted to avoid the town, Atherton officials would rather have the train run through a trench or tunnel, instead of on an elevated berm.
The scheduled speakers at the meeting are: Mike Garvey and John Litvinger, public outreach consultants working for the California High Speed Rail Authority; John Townsend, executive vice president of Hatch Mott Macdonald, a leading tunnel-engineering and construction firm; Duncan Jones, Atherton's public works director; Gary Patton, attorney and former director of the Planning and Conservation League; and Jim McFall, who will present a digital model of elevated high-speed rail tracks going through Palo Alto.

I'm really curious about this "digital model" that will be shown. Is it going to be an accurate representation of what an elevated solution could look like, or is it going to be a biased depiction of some kind of Berlin Wall? I hope that the CHSRA has been able to generate some more accurate and realistic digital images of their own.

Update: Thanks to Clem in the comments who links to Jim McFall's video - videos that put the worst possible spin on this, making the HSR grade separation look like an Orange County freeway.

Additionally, I'm curious what the tunneling exec will have to say. Will he explain the price tag of a tunnel? Will Atherton residents have their checkbooks and credit cards ready to go to pay the multi-billion cost of such a tunnel? Only one way to find out - go to the meeting!

If anyone does attend, and wants to write up their impressions of the meeting(s), I'll be happy to post it here unedited.