Monday, May 4, 2009

HSR Phase One Yards

NOTE: We've moved! Visit us at the California High Speed Rail Blog.

8 May 2009: In response to a complaint regarding slow downloads of the home page, I've modified this post such that previously embedded videos and maps are now hyperlinks. My apologies for any inconvenience this causes.



by Rafael

While there has been a lot of debate about the route CHSRA prefers and the throughput issues of San Francisco's new Transbay Terminal Center, the issue of maintenance and overnight storage of high speed trains has not received as much attention. However, given the distance between the end points of the starter line for the California network, the success of the service absolutely depends on having enough trains on hand to support operations in the first hours of each day, until the first trains from the other end arrive and are turned around.

Castle Airport: Primary Maintenance Hub

The starter line will be between San Francisco, Los Angeles and Anaheim. AB3034 doesn't explicitly mention San Jose, but the primary reason Pacheco Pass was selected was to ensure that all trains would pass through South City's Diridon station. In addition, phase I will include the wye at Chowchilla and spur up to Merced.

There's been talk of siting the primary maintenance hub at the nearby but underutilized Castle Airport (formerly Castle AFB), which is adjacent to the BNSF right of way. CHSRA wants to prioritize the construction of a test track in the Central Valley, both to help FRA draw up a "rule of special applicability" to enable operations of non-compliant equipment at 220mph and, to help narrow down the list of track and train technology vendors.

So far, CHSRA is holding out for UPRR to cede part of its ROW along CA-99 through Fresno and up to Sacramento to obtain a straight alignment and access to downtown areas, but it's an open secret that rival BNSF has been much more receptive to overtures from the Authority. If CHSRA ends up sticking with BNSF from Bakersfield all the way to Modesto, it would be possible to site the Merced county HSR station at Castle Airport and implement a bypass around the town.

HSR Phase One Yards: Castle Airport

Unfortunately, Merced county lacks a major population center. Without any commercial flights (high speed cargo and/or passenger), an HSR station at the airport would struggle to attract enough ridership to justify running more than a a small number of trains per day to SF or LA/Anaheim in phase 1. That means early construction of a spur up to Castle Airport would primarily be for testing and maintenance. A secondary objective would be a show of good faith that the planned extension to downtown Sacramento really will be built in phase 2.

Here are a couple of videos showing SNCF's and JR's maintenance yards in Villeneuve (near Paris) and Tokyo, respectively. The equipment required depends on the train technology selected. Note that JR has special "Dr. Yellow" trains that measure track geometry, the condition of the overhead catenary system and verify signaling performance while running at 270km/h (approx. 170mph).
Overnight Parking: Northern California

In addition, it's common for railroads to operate yards for overnight storage and at least minor maintenance (incl. thorough cleaning and provisioning) near both ends of major lines because that where trains naturally end up at the end of the day. In the specific case of the starter line for California's system, that means San Francisco and Anaheim, but throughput constraints on the Fullerton-Anaheim section mean that many trains will have to terminate in Los Angeles instead.

Considering that non-stop express runs between SF and LA are expected to take 2h38m, it seems reasonable to say that the first three hours of operation on weekdays have to be supported by trainsets that were parked overnight. Businessmen and tourists looking to make day trips between these cities will likely generate above-average demand for express service in the early morning (departure 6-9am) and afternoon (departure 3-6pm), with additional demand for red-eye service in the evening (departure 8-9pm). CHSRA's target is to build an infrastructure with sufficient capacity to last for 50, perhaps 100 years. Inevitably, that means planning for ridership levels well beyond anything that can be achieved in the first decade of operations.

In particular, CHSRA insisted that it needs capacity to run 12 trains per hour (tph) each way through the new Transbay Terminal (TBT) in San Francisco. The issue was discussed extensively on this blog, leading to these general conclusions:
  • SF wants to stick with the current, imperfect design to secure a slice of the HSR funds in the ARRA (aka H.R. 1-111th aka the stimulus bill).

  • HSR trains can be actually turned around in less than 10 minutes, provided the TBT is considered a terminal station on a route that nominally begins and ends in Southern California, rather than an old-fashioned "Grand Central of the West" terminus station. Unlike steam and diesel locomotives, EMU trains do not need to be reprovisioned with fuel and water, nor do they need to be brought up to operating temperature before departure.

  • the station throat and tunnel can be improved with relatively minor modifications, there is no need for a radically different solution. Given that Caltrain will also heavily use the TBT, headways inside the tunnel for both services combined could be as short as 3 minutes during peak periods such as morning rush hour. That implies a combined total of 20tph, though such a schedule would leave little room for recovering from a delay caused by an off-design condition.

  • given the long walk to the nearest BART station, there is considerable doubt that the TBT could attract enough HSR ridership to justify operating 12tph. For long-term capacity planning purposes, a target of 8-10 HSR trains per hour (each way) was suggested, especially in light of the fact that HSR trains are up to 1320 feet (400m) long and that bi-level rolling stock officially rated at 200mph has been in commercial operation in France since 1996. Each full-length TGV Duplex offers 1090 seats, about 8-9 times the number on the Boeing 737s operated by Southwest Airlines. It will be a while before duplex HSR trains are needed in California.

  • if need be, some northbound trains could terminate in Millbrae or else in San Jose and return south the next morning, without ever having reached the TBT.
The TBT itself will feature six full-length platforms, of which four are supposed to be reserved for HSR trains. This hard allocation relates primarily to differences in platform height, an issue the two operators ought to resolve by seeking the requisite waiver from CPUC. As things stand, this would imply the ability to store four full-length trains overnight at the downtown station.

Assuming a frequency of 10tph for the first 3 hours of each weekday and, that each train could one day be a full-length assembly of two trainsets, that implies a need for a yard near SF with space for at least 26 full-length trains - preferably 28 so one can be a spare while another undergoes maintenance. Caltrain's 4th & King station does not have enough capacity and anyhow none to spare.

There simply aren't that many locations where so many full-length trains could possibly be stored and secured near SF, so it makes sense to buy the land now to avoid a capacity bottleneck down the road. One obvious option is the huge old SP yard at Bayshore (h/t to Clem), which is undeveloped but part of a development project (h/t to DaveO) that does not yet account for HSR. The location is still being decontaminated but actually has space for at least 50 full-length trains. Part of the area could be used to store Caltrain equipment or, as a transshipment facility for High Speed Cargo. All this is assuming the City of Brisbane is interested in once again hosting a rail yard, perhaps with development of the airspace above.

A big issue is that CHSRA currently intends to switch from the inside tracks south of Bayshore to the outside tracks north of it because of the four Caltrain tunnels. However, accommodating UPRR may yet force CHSRA to switch to the two western tracks instead - the issue of track assignments along the Caltrain ROW is fundamental but not yet resolved.

HSR Phase One Yards: Bayshore yard

A second-best alternative to a Bayshore yard might be found in the relatively undeveloped southern part of Mission Bay.

Either way, HSR trains could make the short run from the yard to the TBT in the morning (and vice versa at night) or else, some trains could make Millbrae/SFO their first stop of the day. While CHSRA is pessimistic about boardings/alightings at that station, a number of commenters have pointed out that it would be cheaper to build and use multi-story car parks there than in downtown SF once the area around the TBT is converted into a transit-oriented district. In addition to customers hailing from the north peninsula and central East Bay, residents of western SF may well prefer to ride BART out to Millbrae rather than board at the TBT.

If San Jose Diridon is expanded to two levels, there should be space for an additional 4-6 full-length trains there. The Merced county maintenance facility could easily contribute another 12. All in all, Northern California would have more than enough overnight parking, maintenance and HSC capacity if CHSRA acquires the Bayshore yard. It should not matter that BART will usurp the entire Newhall yard in Santa Clara.

Overnight Parking: Southern California

The number of trains traveling north between 6 and 9am need not be the same as the number traveling south. Over the course of a staggered 15-hour day, any train can comfortably travel twice in each direction, such that it would always be parked overnight in the same yard. That means the division of trainsets between northern and southern California can be based on passenger demand during the peak periods. It also means crews can be operated in two shifts of 7.5 hours each. Depending on the contract, weekend and holiday service could be implemented via a scheduled 45-hour six-day work week and a total of six weeks paid vacation per year.

In the absence of directional ridership data, I will assume a requirement to operate 10 tph out of LA and Anaheim combined to SF during the morning peak period, which spans 3 hours in LA but 3h30m in Anaheim, incl. a 10 min layover at Union Station. LA Union Station will feature a second level with perhaps six full-length platform tracks for HSR plus run-through tracks on aerials. Anaheim ARTIC will have room for perhaps four full-length platform tracks. That means one or more yards for an additional 21+2 full-length parking spaces may be needed.

One option would be a new yard just west of ARTIC in a utility ROW between I-5 and South Claudina Way, sufficient for 13 tracks in addition to the electricity pylons and telephone poles already present. Normally, trains would only use the turnoff toward ARTIC. Note the brown line representing a potential extension of the Metrolink network in Orange County, linking LA US, Long Beach airport, Disneyland, ARTIC and John Wayne Airport (zoom out to see the route). Some tunnel sections would be involved, in those the locomotives should switch to third rail electric power (e.g. 1500VDC).

HSR Phase One Yards: Anaheim

However, note that the Fullerton-Anaheim section will be dual track and limited to about 3 HSR trains per hour. That means only 7+2=9 slots will actually be needed, leaving plenty of room for the utility poles and pylons plus two potential Metrolink tracks.

That implies a further 14 spaces would be needed in Los Angeles. One option would be a second level above the Metrolink yard at South Santa Fe, just south of Union Station. This could actually accommodate up to 16 full-length trains.

HSR Phase One Yards: South Santa Fe

The snag is that an elevated yard would be very expensive to construct. A better option may be an at-grade yard north of LA Union Station, next to North San Fernando Rd. It may be possible to park 14 full-length trains in that triangular patch of land.

HSR Phase One Yards: North San Fernando

An additional issue is that there will be local HSR trains within Southern California once the phase 2 spur to San Diego is built, so additional yard space will be needed. Palmdale airport would be a good candidate, especially if a new passenger terminal with an integrated HSR station is constructed approximately half-way in-between Palmdale and Lancaster. It should be easy enough to design platform + storage tracks for e.g. 20 full-length trains at this new transportation hub. In practice, fewer may be needed, this depends in part on if and how CHSRA and DesertXPress choose to integrate their services.

HSR Phase One Yards: Palmdale

Conclusions

Finding adequate yard space for Phase 1 looks feasible, though there are constraints in both Los Angeles and Anaheim. However, CHSRA doesn't have a whole lot of viable options if it wants to keep the total number of yards manageable. That means it should purchase the Bayshore yard near San Francisco plus land for a new North San Fernando yard and a third near South Claudina Way in Anaheim sooner rather than later.

Yard space at Castle and Palmdale airports should be cheap and plentiful, but its unclear how useful that would be early on. There are currently no firm plans to build a new passenger terminal with integrated HSR station at either one, though LAWA is on the hook to some extent because it used its influence to ensure the route would run past Palmdale rather than across the geologically more challenging Grapevine. Developing the currently-defunct Palmdale airport into a facility that attracts large numbers of passengers and airlines depends critically on a sound development plan. Right now, LAWA is looking at using part of the land for a solar thermal power plant, which could potentially cause glare problems. There are also plans to develop the Antelope Valley, i.e. north-east LA county, via conventional low-rise sprawl rather than transit-oriented high rise towers that are more easily cooled and supplied with non-potable recycled water in addition to a constrained supply of potable water.

Saturday, April 4, 2009

Sacramento Bound

NOTE: We've moved! Visit us at the California High Speed Rail Blog.

In recent months, whenever we mentioned Sacramento on this blog, it was in the context of state politics - especially the saga of AB3034 (the bill enacted by proposition 1A), the even more tortuous state budget process and its impact on CHSRA. Yet there is also a bona fide HSR spur from Merced to Sacramento that is planned for phase II of the project and that we've not given the attention it deserves. Like the spur to San Diego and the extension to Irvine, this will be funded using non-state bonds backed by net positive operating revenue from the starter line, which may take several years after start of operations (2018-2020 time frame) to materialize.

In other words, actual construction on the spur to Sacramento won't begin until 2023-2025 and the first trains won't run into the state capital until several years after that. That's a very long time to wait, but the city is already busy planning for its bullet trains. Specifically, a huge 240-acre site northwest of downtown is being developed as a mixed-use transit-oriented development that will preserve and partially re-purpose the historic rail yards at its center.


View Larger Map

The part of greatest interest to us on this blog is the Sacramento Intermodal Transportation Facility (SITF), which will be located just south of the historic yards. UPRR and Amtrak will remain at grade but the alignment between the rail bridge across the Sacramento river and 7th/D will be straightened out starting this year.

An overview of the SITF component of the redevelopment project was presented at a recent workshop. Still to be decided is if the historic depot (station) should remain where it is or be moved 500 feet north. The latter would create a more compact facility and free up space for general development on the downtown side of the site.

Either way, the light rail transit (LRT) station for the SITF will be relocated to the east, near 5th Street. Among other lines, Sacramento is planning one out to SMF airport via the Natomas district. It will be a slow ride with a total of 13 stops and, the airport station appears to be far removed from the two terminals. It's unclear how successful the service will be at attracting passengers with baggage - most of those connecting at the SITF will probably prefer a taxi or shuttle bus. The project has progressed to the project EIR/EIS stage for the first mile along 7th Street, but it doesn't appear to integrate into the design options for the SITF depot at all well. Either the documentation is out of date or, the left hand doesn't know or care what the right is doing. It's not intermodal if you have to walk two blocks.

Just north of the new LRT tracks will be the relocated run-through tracks for UPRR and Amtrak. The area reserved for these will accommodate two island platforms for a total of 4 platform and two through tracks on the outside. To avoid the freeway supports, designers moved the islands further from the river than strictly necessary and tacked on severely curved sections at the eastern end. The straight sections are approximately 250m (800ft) long. The HSR station would be a terminus featuring what appear to be 10 full-length tracks on an upper level, with a concourse in-between. It's not immediately clear if the current plans for the SITF already reserve enough space for all ten elevated tracks.



Elevating the HSR tracks implies two things: first, that HSR trains will never cross the Sacramento river. And second, that UPRR agrees to let CHSRA run an aerial structure above its own tracks on the way to that station. Please zoom in on Sacramento for details of the implementation CHSRA used for cost estimation purposes.

As we have recently discussed (How Important Is UPRR To California HSR?, Union Pacific Speaks), it is far from clear that UPRR will in fact agree to this concept. If so, CHSRA could find it very difficult to reach the SITF at all. East of 46th Street, CHSRA intends to run at grade, except for short sections in Elk Grove, the Lodi bypass and downtown Stockton. All of those aerials are overpasses of other rail lines or freeways. South of Stockton, CHSRA is counting on the UPRR ROW that runs east of the Sharpe Army Depot and is currently used by ACE. Between Manteca and south Fresno, CHSRA would prefer to keep running alongside UPRR tracks and I-99.

It very much remains to be seen if UPRR will go along with all that, early indications are that CHSRA might have to partner with BNSF instead for the south Stockton-south Fresno section. That might mean greenfield bypasses for both Fresno and Merced plus relocating several stations. For example, Merced county may well prefer a station at Castle Airport to the Amtrak stop on W 24th, in a residential neighborhood at least eight blocks from downtown. Considering that express trains will run through the Central Valley at 220mph (as opposed to just 125mph in the mid-peninsula), it's not clear that CHSRA has fully communicated the noise impacts to Central Valley towns hungry for the construction work.

None of the videos produced by NC3D features audio, something that may well come back to haunt the planners. Just how much would it cost to send a sound recording specialist to Europe or Asia, anyhow? Example: grade separations in Fresno.



Sticking with BNSF would mean all of the stations in the Central Valley would be intermodal with Amtrak San Joaquin trains, though it's unclear if that service will remain viable once the HSR network is fully built out. One problem for HSR is that the BNSF tracks UPRR's at very nearly a right angle, with insufficient room for a high-speed corner. One possibility would be to cross over between Escalon and Ortega/French Camp, roughly along an existing secondary rail ROW. The ever-useful 2005 Rail Rights of Way and Abandoned Corridors Study commissioned by Caltrans' Division of Rail (aka Amtrak California) shows this section as active. My guess is UPRR owns it now.


View Larger Map

Even if CHSRA were to bypass Stockton to the east on a brand-new ROW - something that it never even considered - it would still have to deal with UPRR north of Lodi and up in Sacramento. For this spur, even more than any other part of the planned network, CHSRA needs to be in UPRR's good graces.