It's pretty much a formality at this point, but Judge Michael Kenny has issued his final judgement in the case of Atherton v. CHSRA, ordering the CHSRA to revise the EIR for the Bay Area to Central Valley segment of the project to address the concerns over noise/vibration and ROW sharing with UPRR that the judge cited in his initial decision. See both the Final Judgement document and the Peremptory Writ of Mandate below, and then my comments:
Final Judgment in Atherton v. CHSRA
Peremptory Writ of Mandate
As we explained earlier, the judge rejected plaintiffs' request to stay further HSR work. According the the CHSRA, this outcome does not impede them from continuing to move forward as they currently are with project-level EIR and design work, and should not jeopardize stimulus funding. The judge did not order a complete reopening of the full EIR process, and CHSRA is confident they can submit the revisions on time. The judge gave CHSRA 70 days to show their compliance (by decertifying the EIR - they have more time than that to finalize the revisions; thanks to the comments for pointing this out) although exactly what that means isn't precisely clear in the documents.
Although we'll hear the project opponents and those that filed the lawsuit claim victory here, it's difficult to see how those claims can be justified. The Pacheco alignment is upheld, CHSRA can continue to plan and design the system, they'll still be getting federal stimulus funds, and the judge has given them wide latitude in how they comply with the order to revise the EIR. Furthermore, the overwhelming majority of the plaintiffs' claims, particularly the main ones about the Pacheco alignment, were thrown out. The plaintiffs basically got lucky in that the judge found some other parts of the EIR that the plaintiffs never really focused on were deficient and necessitated a revision.
What was promised to us in the summer of 2008 as a lawsuit that would stop the project in its tracks and blow up the route decision has essentially fizzled. CHSRA will produce an improved EIR and address the UPRR issue, something they needed to do anyhow. The plaintiffs will get their court costs paid, but otherwise they've failed to accomplish their goals of undermining the HSR project.
Tuesday, November 3, 2009
Final Judgement in Atherton v. CHSRA
Friday, October 30, 2009
Does Russell Peterson Know What He's Doing?
In response to a recent Wired Magazine article that declared "NIMBYs won't be able to stop California HSR," one of the more prominent Peninsula NIMBYs, Russell Peterson, decided to not go gently into that dark night. He wrote an email in reply to the article that was itself posted on the Wired site this week. It's a remarkable piece of cognitive dissonance - Peterson is suing to demand that Union Pacific's rights to the Caltrain ROW be recognized as giving UPRR a veto, while at the same time calling for a tunnel to be built on the corridor. The problem with a tunnel, of course, is that it makes it difficult - not impossible, but difficult - for UPRR to continue freight service on the route.
To be clear, the lawsuit (.pdf) is the least intrusive legal action one can take. It is called “declaratory relief” and simply asks for a legal interpretation of the existing contractual rights of Union Pacific. Union Pacific did sell the right of way to the Peninsula joint powers board, but it retained permanent rights. One of those rights, exclusive development of intercity rail, and the exclusion of high-speed rail development on a portion of its right of way makes the situation unclear. And Union Pacific has written letters (.pdf), in May 2008, to the California High-Speed Rail [Authority] stating it will not allow high-speed rail on certain sections of the right of way it owns outright. To imply otherwise is a factual error and a misleading statement in the article.
The problem is that Peterson is overstating his case. Caltrain has argued
8.3.(c) In the event that Owner demonstrates a reasonably certain need to commence construction on all or substantially all the length of the Joint Facilities (including User's Cahill/Lick Line) of a transportation system that is a significant change in the method of delivery of Commuter Service which would be incompatible with Freight Service on the Joint Facilities (other than User's Cahill/Lick Line), Owner may, at its sole cost and expense, file no sooner than nine months prior to the commencement of such construction for permission from the ICC to abandon the Freight Service over the portion of the Join Facilities (excluding User's Cahill/Lick Line) upon which the construction is to occur. User shall not object to or oppose such a filing; however, it shall be allowed to participate in the abandonment proceedings.
Of course, Caltrain and CHSRA have shown no desire to kick UPRR off the corridor. Much to the contrary - they are already in discussions with each other about accommodating existing freight rail service.
And that is going to be difficult to do with a tunnel. The tunnel would have to be high enough to allow overhead wires to give clearance room for double-stacked container cars, and would have to have adequate ventilation for diesel locomotives, since it is extremely unlikely that UPRR will use electric power for this route alone.
That would undermine Peterson's stated support for a tunnel:
Likewise, Caltrain rail experts told a civic audience on Oct. 3 that a tunnel is not even twice as expensive as current plans for elevated rail. Given that environmental and other required mitigation costs add significant expense to the elevated option, the tunneling proposal offers interesting development opportunities along the route. Besides these opportunities it seems odd to promote 21st-century high-speed rail and then proceed to plan a 1950s- and 1960s-style elevated structure. The not-so-subtle inference that opponents are NIMBY is simplistic. Boston’s “Big Dig” buried a major freeway, the Loma Prieta earthquake took out the Cypress Freeway (now a park with renewed neighborhoods, etc.) and the Embarcadero Freeway (which led to renewal of the Ferry Building and surrounding area), and Berkeley buried its rail (and only paid a 10 percent premium vs. above grade). All of these projects brought both transportation and civic value to their respective areas. Why community involvement/engagement is so readily marginalized is puzzling to me with such clear examples of revitalized communities.
This is basically an incoherent grab bag of claims. First, the elevated structure would not be "1950s- and 1960s-style," there are 21st century methods of building elevated structures in ways that fit well with the surrounding community. San Carlos hasn't exactly been destroyed by its elevated segment. The Big Dig isn't exactly an argument in his favor, and neither the Mandela Parkway nor the Embarcadero replacement projects were tunnels. Finally, Berkeley paid the extra costs of what was mostly a cut-and-cover project by taxing itself to do so. Unless Peterson believes that the mid-Peninsula cities plan to tax themselves to pay for a tunnel, then he'll be looking to the sale of air rights - a sale that won't be possible if UPRR preserves its freight service rights on the existing at-grade ROW.
Peterson's letter continues in this scattershot vein:
The implication of the story is that this project is coming, like it or not. This may be a correct conclusion based on politics and political connections but Zach makes no arguments for it. Eventually he admits opponents rightfully have concerns, then dismisses those concerns. Caltrain recently issued a letter describing the ill effects of raising a source of noise (train horns) 14 feet in the air and how it is working to correct the problem. Well, elevating the whole train to 15 feet and increasing the speed would create more noise — thus Caltrain even agrees. The environmental impact report is deficient — has anyone explored the idea that people expected environmental laws be followed when they voted “for” this project?
Of course, "this project is coming" is based on the fact that the people of California voted for it and expect the HSR project to be built, and not held up or have its costs driven up by NIMBYism. Peterson claims NIMBYs just have "concerns" and want "oversight," but they've never really shown any support for the concept of high speed rail. Instead they prefer to undermine HSR's effectiveness or even its very existence to suit their own needs, believing that their priorities are more important than those of the state as a whole.
As to train noise, this is a complex matter. But one aspect of it is quite simple: on an elevated structure, there will be no more horns, period. Further studies will demonstrate the difference between those horns and the noise made by passing electric trains, which would not be running at full speed along the Peninsula anyway.
If Peterson's goal was to show the world that Peninsula NIMBYs are a principled group of people just trying to help HSR get better, he has completely failed. Instead he has revealed Peninsula NIMBYism for what it truly is: an incoherent collection of arguments held together by a desire to place their own personal vision of urban aesthetics above the vision, the needs, and the stated preferences of millions of their fellow Californians.
Sunday, October 18, 2009
Building an Organic Machine Along the LA River
It is impossible to address the broad crisis facing California without affecting some preexisting plan in some way. Whether it's the transmission lines needed to carry power to cities from a solar plant in the Mojave Desert or the Carrizo Plain or whether it's building a light rail line next to an LA high school or something else entirely, solutions to the economic, environmental, and energy crisis aren't being built on a blank slate. We have to implement them within the built and the natural environment we have, and that means when we want to build high speed rail, it may mean other plans have to be shifted to accommodate it.
The latest instance of this intersection of plans is along the Los Angeles River. If you've ever seen the movie "Grease" you've seen the LA River. Once a meandering seasonal stream which sometimes took an entirely different course to the Pacific Ocean than it does now (prior to 1835 it joined Ballona Creek and emptied into the Santa Monica Bay), it has become a largely concretized flood channel of the kind you see all over Southern California (including in the backyard of the house I grew up in).
Along with this "modernization" the LA River has also become a major transportation corridor. It was always thus, from Native American times to the late 1700s when Spanish padres marked the El Camino Real along its course. In the 1800s railroads were built along its banks, and in the 1950s several freeways, including the Golden State and the Long Beach freeways, were constructed alongside it.
Since the 1970s there have been a series of efforts to restore the "old" LA River by removing some of the concrete, which would both slow down the river (making it less dangerous during winter flash floods) and make it more hospitable to wildlife. There have also been plans to conduct urban renewal along some of the older industrial sections of the LA River, including those areas currently used by trains.
These plans will be impacted by the high speed rail project, and the intersection of those two projects is the topic of an in-depth article in the LA Times today. The article, by Ari Bloomekatz, is generally a good overview of the concerns some of the river revitalization activists have about high speed rail:
The plan to build a network of high-speed bullet trains across California is facing opposition from the heart of Los Angeles, where community leaders fear the line will hurt efforts for another grand project: revitalizing the L.A. River.
The rail plan, which has picked up considerable steam since voters approved the nearly $10-billion bond measure in 2008, would use Union Station as a major hub, and the line probably would run along the Los Angeles River.
But some elected officials and residents believe the proposed rail alignment would seriously clash with their vision for the area, which involves replacing the dilapidated industrial proprieties along the river with green space, recreation areas and community facilities.
The situation makes for delicate politics. Many L.A. officials strongly support the bullet train concept and believe that the Union Station hub would fit into the county's efforts to expand subway and light rail service. But they also believe that revitalizing the river is an important part of making the city core more livable for residents and attractive to visitors.
Part of the problem here is that some of the revitalization advocates do not appear to have considered trains as part of their vision for "making the city core more livable for residents and attractive to visitors." Others, still operating in a late 20th century mindset, see any major transportation project as producing the kind of "blight" they associate with the current situation along much of the LA River. Instead of railroads and industrial zones being a thriving hub of activity, by the 1980s they had fallen into disuse as state and federal policy and economic shifts rendered those sites undesirable. Unfortunately, many took the lesson that "railroads along the river produces blight," which doesn't predispose those types to support a train.
The specific area under discussion in the article is known as the Taylor Yard area of the "Glendale Narrows" - the area alongside the Golden State Freeway and the Metrolink ROW. This region has been an important transportation corridor going back to the Native American days, and as anyone who's been on Metrolink through here knows, it is already heavily used by trains. It is also one of the few places along the LA River that has not been fully concretized - it has what is officially described as a "soft bottom" and is therefore seen as a prime location for ecosystem restoration. But the closure of Taylor Yard suggested to many in the area that the day of the train was done, and that a post-railroad vision for that section of the Glendale Narrows was desirable:
The proposed rail routes would run near Taylor Yard, a 247-acre freight switching facility in Cypress Park that was closed by 1985. Part of Taylor yard, which is north of Union Station, is still used for rail maintenance and storage, but it also includes Rio de Los Angeles State Park and sites for a planned high school, green space and a mixed-use housing development. The Los Angeles River runs next to it.
"To take a step backward, to put in a train, it's not going to help the quality of life," said Greater Cypress Park Neighborhood Council chairman Gustavo Lizarde.
Lizarde grew up in Lincoln Heights, moved to Cypress Park in the early 1980s and 25 years ago took over his father's auto service shop on North Figueroa Street. He used to live near Taylor Yard.
Last week, Lizarde walked past a new soccer field at the park off San Fernando Road to the concrete bank of the river. A blue heron swooped by a path littered with foam plastic cups.
The soccer field is one part of the city's long-term effort to transform the area along the concrete-sided river that was once synonymous with crime and graffiti into a place residents can enjoy.
Lizarde is articulating exactly the vision I described above - one where railroads are bringers of blight. Because Taylor Yard was undesirable in the 1980s, and because that led to it becoming a haven of crime and decay, Lizarde believes that any railroad use of the site would inherently produce those conditions again. To someone like Lizard, the Taylor Yard region exists in a perpetual 1985, where any expanded use of the area by trains would inherently blow up the plans to revitalize the river and the surrounding neighborhood.
LA City Councilmember Ed Reyes, whose district includes the Taylor Yard area, thinks HSR should simply avoid the area entirely, even if it meant abandoning the Union Station terminus:
But if the high-speed rail goes through Union Station, some officials and environmental advocates say, it would be difficult to find a route that doesn't run near the river.
Los Angeles City Councilman Ed Reyes said he would like to see other alternatives for routes from Anaheim to Los Angeles and from Los Angeles to Palmdale. He said he supports the high-speed rail but doesn't want to sacrifice the river or the progress of the communities the bullet train would pass through.
"The river right now is in a straitjacket. Lined with cement, constrained by railroad lines. . . . But the way they're approaching it, they're going to put the last strap on the straitjacket," Reyes said. "I support it, but let's not be hasty, let's be opportunistic."
So what's really going on here? Is there a huge anti-HSR backlash forming in LA that can give hope to the Peninsula NIMBYs? Will community organizers like Gustavo Lizarde and local electeds like Ed Reyes undermine one of HSR's most important, most vital aspects - using downtown LA's Union Station as a primary hub?
Not so fast. A look at the details suggests that not only was HSR taken into account in the LA River revitalization planning process, but that the plans envision HSR as a possible solution - instead of a barrier - to achieving some of the plans's key goals.
First, let's have a look at the area in question:
View Taylor Yard/HSR in a larger map
With a proposed high school and state park in the way, one might think "omg this is totally unworkable." But in fact the issue seems to be whether the San Fernando Road alignment or the existing Metrolink/UP alignment is used. As you can see, the location is already heavily used by rail, and Metrolink's primary maintenance hub is located just south of the Taylor Yard area.
Much of the non-railroad land is owned by the California State Parks. A lawsuit several years ago stopped the city of LA, UP, and Lennar (a real estate developer) from new industrial development on the site. Described as "the brass ring" for river activists, the Taylor Yard area is seen as a keystone in the "green" vision for the LA River.
But what does "green" mean? Does it include electric, non-polluting, sustainable high speed rail? Or does it mean essentially turning the area into a park?
The City of Los Angeles's River Revitalization Plan makes a clear statement that trains are an essential part of the River, and that HSR can actually serve as a method of reconnecting neighborhoods to the River:
High Speed And Light Rail Lines Could Be Opportunities To Connect To The River: While heavy rail poses the challenges noted previously, existing and proposed future light rail lines could be opportunities to connect a multi-modal system with the River....
The proposed California High-Speed Rail system would travel from San Francisco, Oakland and Sacramento in the north to Los Angeles and San Diego in the south, and would connect California’s major metropolitan areas. The proposed corridor alignment has been loosely identified in the Los Angeles area, and it traverses a portion of the project area. The preferred alignment is along both sides of the Los Angeles River: one proposed track crosses the River from Mission Yard towards Union Station and continues south while the other passes through Union Station and splits to cross the River south of US-101 and south of 1st Street. Should the rail system be implemented as studied, it offers the potential to bring visitors from outside the region to the City. A revitalized River could provide an important regional recreational destination, as well as an amenity that could draw more visitors to the City. (pages 3-16 and 3-17)
It also presents an opportunity to reconstruct the tracks in the area - consolidating rail lines and putting them in either a viaduct or a trench, creating the possibility of at-grade connections to a riverfront park. And as that segment of the plan notes, both UPRR and BNSF (which operates further down the river, south of Union Station) are not only heavy freight users of rail corridors along the river, but are likely to explore options to expand the rails to accommodate future freight traffic.
Ultimately the plan makes it clear that rails are part of the River's future, instead of an impediment. Neither the freeways nor the rails are going away anytime soon. In fact, electrified passenger rail is a key element of improving the quality of life in Southern California, including for the residents of the Cypress Park and other nearby neighborhoods.
Few of the people quoted in the article are HSR opponents, and the article itself recognizes the environmental benefits of HSR. The ultimate question here is how to reconcile two efforts to produce environmentally friendly uses of urban land.
What this situation primarily demonstrates is that the issue really isn't about the environment. It's instead about perceptions of what urban life should be like. Some of the neighbors near the Taylor Yard have a fundamentally 20th century vision in mind - they're afraid any new rail projects will return the site to 1985, but their own vision is essentially the 1950s - a low-density community with green space and access to a quiet, meandering river.
In this way they're not so different from the Peninsula NIMBYs, who seem to prefer a permanent 1975, even at the expense of Caltrain's survival. They're all motivated by a belief that trains bring blight, that trains are not a part of a desirable community. That is a belief unique to the late 20th century, but that belief runs deep.
Nobody is yet articulating a truly 21st century vision: one where sustainable land use and transportation, including high speed rail, produces cleaner and quieter communities, bringing economic security for the many and protecting everyone from the looming catastrophes our dependence on oil is about to produce.
The LA River presents a particular problem here. But it's not an unfamiliar problem. Stanford history professor Richard White would have well understood it. In 1996 White, then a University of Washington professor, published a remarkable little book titled The Organic Machine. Ostensibly a history of dams and fish management along the Columbia River, it in fact was something more of a meditation on the impact of modern man on the natural environment.
White's argument was simple: in modern societies, there is no easy separation of the "natural" and the "man-made". A single key sentence explains White's thesis: "We might want to look for the natural in the dams and the unnatural in the salmon." The Columbia River dams became part of nature, and created new ecosystems. The dams brought changes, some of which were positive, some of which were negative. White's goal isn't to praise or damn the dams (heh) but to instead show that for humans to think about saving salmon or managing the Columbia River, they have to accept that there can be no such thing as "purely natural" - instead the river is an "organic machine" whose consequences have to be weighed before they are acted upon.
High speed rail will function as an "organic machine" in California. It will change the surrounding environment, whether that environment is a Peninsula city, a Central Valley grassland, or the banks of the Los Angeles River. And it won't have been the first - compared to the urbanization of California, the agriculturalization of the Central Valley, the building of the first railroads and freeways, high speed rail is really just an upgrade of the existing machine to make it more environmentally friendly and more effective.
And it can serve as an "organic machine" along the Los Angeles River. It can reconnect neighborhoods to the river depending on how the tracks are built. It can help produce a cleaner river, a cleaner sky, and a more sustainable use of the river's watershed. Lizare and Reyes want to see HSR as some kind of invader. It's not. It's instead a way to reconnect human uses of land, just as it is in Palo Alto.
Ultimately what all this shows is that in building HSR, we aren't battling "NIMBYs." We're battling an obsolete model of California. The key dividing line is whether people see a train as a valuable part of the future, or an unwanted relic of the past. Palo Alto residents who design tunnels for HSR are embracing the possibilities of HSR, whereas those who sue to kill the project just don't seem to want trains around at all - including Caltrain, which their HSR denial is putting in jeopardy.
There are ways to revitalize the LA River and build HSR at the same time - and in the same place. Let's hope that residents and lawmakers prefer to embrace a 21st century vision of high speed rail as an organic machine, instead of the 20th century vision of trains as an undesirable and somewhat embarrassing reminder of a past they have rejected, for a present that has totally failed the vast majority of Californians.
UPDATE: Thanks to Rafael, have a look at the CHSRA's Taylor Yard simulation video, produced by NC3D. It shows that in both the Metrolink and San Fernando Road alignments the tracks would be trenched, and there would be two "lids" connecting the Cypress Park neighborhood to the Rio de Los Angeles State Park and riverfront. To see a good example of a "lid", look at the Mercer Island Lid, built over Interstate 90 on Mercer Island, Washington in 1993. The park is a very popular location in one of the Seattle metro's wealthiest communities and does an effective job of providing green space connectivity over a major transportation corridor.
Assuming CHSRA is able to construct the trench-and-lid model shown in the video, the complaints offered in the LA Times are much ado about nothing.
Thursday, October 8, 2009
Judge Kenny: Planning Work Can Continue
Judge Michael Kenny has issued his tentative ruling in the issue of whether work could continue on the Bay Area to the Central Valley segment of the high speed rail line - and it is a victory for CHSRA:
Petitioners have requested that the writ of mandate to be issued in this case include a stay of all of respondent’s activities dependent on or premised upon the approvals being ordered rescinded. Respondent opposes the request. The Court set a briefing and hearing schedule on this issue.
The Court has considered the parties’ arguments and the evidence they have submitted on this issue. The Court concludes that under the circumstances of this case, staying project-level activities is not appropriate pursuant to Public Resources Code section 21168.9(a)(2) and pertinent case law.
The actions for which a stay is being requested are studies with no potential for adverse change or alteration to the physical environment. Additionally, the Court concludes that such studies do not create such momentum that respondent Authority would be unable to comply with its CEQA obligations as previously determined by this Court.
Accordingly, petitioners’ request that the writ to be issued include a stay is denied.
CHSRA offered this statement in response:
“We’re happy to see that the tentative ruling supports our position that granting a stay on the project is unnecessary since the project is in the planning stage and could cost the state funding and jobs,” said Jeff Barker, the Authority’s Deputy Director.
"We don't believe that anyone is interested in jeopardizing billions of dollars in economic stimulus for California, delaying the creation of tens of thousands of jobs, and forcing taxpayers to shoulder higher costs to build the system," said Barker.
Totally agreed. There was no reason to delay planning work while the CHSRA goes back to address the two items that Judge Kenny said were inadequately examined in the program EIR.
Once again the HSR deniers behind this lawsuit have lost. They basically got lucky on the UPRR ROW issue, which was never a core element of their lawsuit, and their other efforts to stop HSR in its tracks have been consistently shot down by this judge. I have every reason to believe that will continue.
Monday, October 5, 2009
Has Palo Alto Turned The Corner?
Over the weekend Palo Alto hosted an HSR design workshop that included working groups focused on a number of different neighborhoods in Palo Alto, Menlo Park and Atherton. I wasn't able to attend owing to last-minute work commitments. But judging by the reports, it was an extremely productive event where residents came up with their preferred plans - and even explored ways to pay for them.
If you were there, by all means, post your thoughts in the comments. For now, I'm going to have to rely on the local press. Sue Dremann at Palo Alto Online had a good overview:
The two-day workshop, sponsored by the Peninsula Cities Consortium, brought together residents, city and Caltrain officials, architects, and experts in transportation, geology, tunneling, historic resources, finance and public art to discuss the visionary futures for the rail corridor.
The consensus was for undergrounded tracks with parks, community gardens, a bicycle boulevard, green spaces, shops and streets to connect neighborhoods now divided by the at-grade and elevated tracks....
Most groups said tunneling the trains seemed the best alternatve -- but they recognized the complexity and cost. The groups considered boring deep beneath creeks and avoiding damage to El Palo Alto, the city's iconic redwood.
Dremann's article goes into some detail on the various neighborhood proposals, but I want to focus on the bigger picture. Assuming this is an accurate reflection of the event, I am extremely pleased to hear this. I've always been open to a tunnel - the question is instead the cost, and according to Dremann, the locals fully understand it:
Some groups suggested the project could be funded by a one-percent sales tax hike, as was done in Berkeley when Bay Area Rapid Transit (BART) was built. Others suggested a voter-approved 30-year property-tax fee could cover costs.
Both funding models are sensible, since they rightly recognize that they will have to pay for a tunnel themselves. If these cities can muster the public support to approve such a tax, and if they can show it will pay for the costs of the tunnel, then I'll be one of the biggest supporters of such a plan.
Funding an underground solution is not likely to be a simple matter. Gennady Sheyner's Palo Alto Online article makes that pretty clear:
But speakers at Sunday's workshop also acknowledged a major obstacle standing between them and their idealistic vision: the high cost of creating underground tunnels. While rail officials don't expect to have a cost estimate for the project for another year, they have estimated the cost of boring tunnels to be about 6.5 times as much as building at grade.
The cost of building underground tunnels is also expected to be beyond the rail authority's $4.2 billion budget for the Peninsula segment.
Glenn Isaacson, principal at Conversion Management Association, said cities would have a hard time funding a tunnel, but offered several ways in which it could be done. Aside from passing bond measures or enacting special taxes, cities could sell land currently occupied by the Caltrain right-of-way and use the proceeds to pay for the tunnels, he said.
Workshop participants have also singled out a downtown stretch between El Camino Real and Alma Street as a possible site for dense, revenue-generating developments, including multi-story condominiums. But Isaacson warned that the project would still likely require significant additional funding from the California High-Speed Rail Authority.
"I'd urge you to watch your pennies in the cost of what you select," Isaacson advised the audience. "You'll have a hard time covering 100 percent of the gap."
My guess is they'll have to do all of the above - property assessments, passing a bond, and selling air rights - to fund an underground solution. One possible solution is for the CHSRA to lay out the cost of an above-grade solution (some of these articles mention an "at-grade" implementation as a possibility, which it is not) and then tell the locals that if they want to go above and beyond by building a tunnel, they have to pay for those added costs.
If you want to get public support for paying those costs locally, you have to sell not the process, nor the technical solution, but you have to sell a vision. A vision of a better Peninsula. And that too is something that the locals understand:
California's high-speed-rail project could offer Palo Alto and its neighboring cities a rare opportunity to revitalize their downtown districts, transform old train tracks into leafy gateways and bring neighborhoods closer together, a group of leading urban designers and architects said at a Sunday workshop....
Judith Wasserman, a member of Palo Alto's Architectural Review Board, gave the plan a special name: "Together Again for the First Time." Wasserman said an underground system could offer the city a long-awaited chance to connect its neighborhoods.
"The town has always been divided by the train," Wasserman said. "We've never had good cross-town connection. This is an opportunity we'll never have again."
Of course, Wasserman has it backwards; the train was there before the town. But that shouldn't take away from what is a very reasonable and supportable vision for how HSR can enhance and improve the local community.
That all being said, there are two huge, related caveats that we all need to keep in mind before we pronounce the corner being turned on the Peninsula HSR debate.
The first is the above-grade solution. It makes sense for everyone involved to have the community do work on determining how to implement an above-grade four-track solution in a way neighbors can live with. Neither Caltrain, the CHSRA, nor the Peninsula cities can afford to pin their hopes on getting voter approval for a tax increase to build a tunnel. Such work may have been done this weekend and just didn't make its way into the reports, but it is vital that the design workshops include an emphasis on planning above-grade solutions.
The second is freight rail. As we saw at the Palo Alto teach-in last month, the Peninsula Freight Rail Users Group is adamant that freight rail continue to operate much as it does today, and Union Pacific has its trackage rights that have to be considered as well. It's theoretically possible to design a tunnel that could accommodate freight rail, but the design for that is very, very different from tunnels for passenger trains alone. Since many of the proposals for tunneling in Palo Alto and neighboring cities revolve around using the at-grade land for purposes other than a railroad, that means they're going to have to build a tunnel big enough to possibly accommodate 4 tracks and high enough to accommodate today's containerized double-stacked freight consists.
I don't know if that all was discussed at the workshop. But it should have been, and it needs to be discussed going forward. Otherwise what was a very productive and valuable planning workshop may not actually be as effective as it ought to be.
Saturday, October 3, 2009
What To Do In Willow Glen?
UPDATE: Note that in fact the tracks from Diridon Station to a point called "Lick" 3 miles south, about where the tracks reach Monterey Highway, are owned by the Peninsula Corridor Joint Powers Board (PCJPB), as Rafael pointed out in the comments. I've updated the post to reflect that info.
This weekend Peninsula residents are gathering at the Palo Alto Sheraton to discuss possible designs for the Caltrain/HSR project through Menlo Park, Atherton, and Palo Alto. I'm going to have to miss this event, but it's worth noting their task is significantly easier than the much more complicated and difficult question of HSR implementation just a few miles down the tracks in San José.
The Willow Glen and Gardner neighborhoods, located in the heart of the Silicon Valley, are wrestling with the question of how to implement HSR through their communities. Like their neighbors on the Peninsula, they too have an existing railroad running through their community, which as on the Peninsula predated the homes.
But unlike the Peninsula, Willow Glen and Gardner in particular have other major transportation systems impacting and dividing their neighborhoods. I-280 and the CA-87 freeways have already cut through significant portions of both areas. These neighborhoods also lie in the flight path of Mineta San Jose Airport, whose runways are located about 2 miles or so to the north, meaning there is significant aircraft noise in this neighborhood.
Finally, and perhaps most importantly, the existing tracks south of Diridon Station a point 3 miles south of Diridon called "Lick" (thanks to Rafael for the clairification), currently used by a few Caltrains to/from Gilroy and the twice-daily Coast Starlight, are owned by the Union Pacific Railroad. The ROW through the Gardner neighborhood appears to be wide enough to accommodate four tracks, including the existing two that comprise the northern end of the UPRR Coast Line. Of course, as we know, UPRR is not in a mood to actually share that ROW. And that causes a significant problem for both HSR planners and the surrounding neighborhood. (Again, noting the correction above, the segment through the Gardner neighborhood is indeed owned by PCJPB.)
View Willow Glen/Gardner in a larger map
That's why the CHSRA is hosting a community meeting at the Gardner Community Center Tuesday, October 6 from 6 to 8pm to discuss the issue. As the Mercury News explains it, the popular proposal in Gardner and Willow Glen is to move the tracks to Highway 87:
Residents of Willow Glen and the Greater Gardner area including David Dearborn, Jean Dresden, Michelle Harris and Harvey Darnell submitted pages of questions for the "scoping" document that will set the parameters of the draft environmental impact report.
Dresden and Dearborn — who has worked in technical fields for 30 years — drafted a plan called "Thread The Needle," which describes in detail how the rail line could trace Highway 87 through the Interstate 280 interchange. It would run underground in the Delmas Park area to the Diridon train station.
Rail leaders say perhaps a compatible option would be to replace the Valley Transportation Authority's light-rail line along Highway 87 with a high-speed line, although it is unclear if the VTA would allow it.
I'd love to see this plan, which I could not find online, because I'm quite curious about how this would work in practice. Moreover, I'm also quite curious about how the hell VTA would continue light rail service on the Santa Teresa and Almaden lines if their median tracks in Highway 87 are taken, even if just for the few miles between Curtner Ave and the 280 interchange. VTA light rail is a "struggling" system, but as Yonah Freemark at The Transport Politic noted, better land use policy in the Silicon Valley would help make the system much more effective. The "Thread the Needle" plan seems to suggest abandoning light rail along the Highway 87 corridor almost entirely (which is one reason I want to see the actual plan). You can't actually widen the Highway 87 to accommodate both HSR and light rail tracks, since to do so you'd have to encroach on the same
Neighborhood residents say they support the HSR project, even though they exhibit the same errant thinking about the place of rails in communities as some folks on the Peninsula:
Michelle Harris, a 48-year-old Cisco engineer who lives on Fuller Avenue, said many people in the Gardner area want the route moved to Highway 87.
"In older neighborhoods, the Caltrain tracks go through quaint parts of town. Putting a 200 mph train through it is kind of like putting a freeway through it," Harris said.
Harris, the secretary of the North Willow Glen Neighborhood Association, also said that many neighbors support the rail project and voted for Proposition 1A in 2008. They want to be close to a train station that would take them to other cities, she said.
As you can tell, the problem here is that Harris has it backwards - the neighborhood "goes through" the rail corridor, which was there before the houses. But what about the "200 mph train" - is that actually what would be implemented in the neighborhood (and even if it were, wouldn't the noise be FAR less than that of the two existing freeways and certainly less than the existing Caltrains)?
Rail leaders have said in public meetings that trains would travel about 60 mph if they negotiated the curves of the Caltrain line through the Gardner area, but they did not deny that noise and vibration would be issues unless soundwalls or tunnels were built.
Notice, of course, that saying noise and vibration would be "issues" isn't the same as saying they'd impact the neighborhood the same way as a freeway would.
In the end, the real issue here is UPRR. Running HSR trains through Gardner at 60 mph on the existing tracks (it's just beyond Diridon Station, so you have to assume trains were never going to be running a whole lot faster than that) would be a perfectly sensible solution that would cause the minimum impact on the community. But since UPRR refuses to allow
Here again I renew my call for California's federal representatives to get involved. As the only body with the ability to actually push UPRR to be more willing to share its ROW. As a creation of the US government, with much of its land and ROW given to it freely by the government, UPRR should be more willing to find a reasonable accommodation with the HSR project.
Monday, August 31, 2009
Media News Group Launches Another Anti-HSR Editorial Attack
One of the most reliably anti-HSR voices in the state is the Media News Group, publisher of several major newspapers (including the San Jose Mercury News). During the 2008 campaign they were among the most die-hard HSR deniers. Now that a judge has issued a mixed decision in the Atherton v. CHSRA lawsuit, MNG is taking advantage of the situation to yet again try and kill high speed rail:
OFTEN THERE IS a wide gap separating a concept from reality. Such is the case with California's high-speed rail project. Conceptually, fast, comfortable, fuel-efficient, intercity, passenger rail transportation makes a lot of sense as fuel prices rise and reductions in carbon dioxide emissions are mandated.
However, there are a number of inconvenient realities that come between California's dream of high-speed rail service and actually constructing it.
The latest roadblock is a court ruling that the High Speed Rail Authority's environmental impact report is "inadequate." The court's conclusion is hardly surprising considering that the EIR failed to address Union Pacific's decision not to allow the trains to run along its tracks from Gilroy to San Jose.
It never ceases to amaze me how usual standards of journalistic practice, such as they are, don't apply at all to the editorial page. The judge most assuredly did NOT rule that the EIR as a whole was "inadequate." He ruled that three specific parts of it were inadequate, but that the overwhelming majority of the contested portions were perfectly adequate, including the basic elements of the choice of the Pacheco Pass over the Altamont Pass for the HSR route. This inconvenient truth doesn't stop the MNG editorialists from plowing ahead with further bits of disinformation:
When the high-speed rail project was first proposed, supporters assumed it would use the Union Pacific's tracks. Without Union Pacific's right of way, an alternate route would have to be considered, affecting the Monterey Highway or requiring the taking of additional private property.
The ignorance here is astounding. UP's tracks were NEVER going to be used, at least not in any plans I've seen over the last two years. I can't speak for the CHSRA, but this HSR supporter never expected to use UP's ROW either. Ever since I became familiar with the situation in May 2008, I understood the plan was to use land next to UP's ROW, but not the ROW itself. Additional private property may have to be taken, but as southern Santa Clara County region is much less built up than the Peninsula, this should not require much if any loss of housing.
As a result of the court's ruling, the rail project is likely to be considerably delayed as a new EIR is written and the additional time and costs of buying land or battling Union Pacific in court are considered.
This is blind speculation almost entirely lacking in evidence. We have no indication what remedy the judge will order. A new EIR does not seem likely, and although it is a possibility, MNG has no basis whatsoever to assume it is a definite outcome. The time and cost of dealing with UP is certainly a consideration, but as I explained yesterday federal assistance can expedite this process.
Alternate routes, such as one over the Altamont Pass, which some rail advocates favor, are even more costly and also would require a new EIR.
Well, at least they got that one right. Altamont is dead. Will groups like the Planning and Conservation League finally accept that reality and devote their efforts to actually supporting HSR?
Voters approved a $9.95 billion rail bond measure last November. The rest of the money is supposed to come from the federal government and investors. Delays can only increase the costs and discourage investors.
But that is hardly the only problem with the high-speed rail project. The business plan is inadequate. There is no accurate estimate of ridership, fares, operational costs and investor interest. Also, the $40 billion cost estimate is dubious.
I see MNG decided to rehash a bunch of the old discredited HSR denier nonsense for good measure. I suppose this means that once we've discredited this editorial we can expect its claims to keep reappearing in MNG editorials for years to come?
With so many other greater capital project needs such as fixing the Delta, highway repair and school renovations that require large amounts of funding, California should sidetrack its highly questionable high-speed rail project.
This is the new line of attack against HSR, and we heard it in Menlo Park last week: that HSR isn't worth the money given all the other priorities.
The fact is we need to and can do all of these things. HSR is necessary to this state's future. To sacrifice it because we're too cheap to find money to pay for our other priorities would have been like refusing to build the Golden Gate Bridge during the Depression. That move, funded by local bonds issued in the depth of the Depression, worked out pretty damn well for California. So too will HSR. MNG will never admit it, and that's fine. We didn't need them in the campaign to pass Prop 1A, and we don't need them in the campaign to ensure that the will of the voters is respected and the HSR project built.
Sunday, August 30, 2009
CHSRA and UPRR Are Talking
Whether it's a prelude to a grand bargain or not isn't clear, but Gary Richards is reporting in the Mercury News today that UPRR and the CHSRA have begun discussions about resolving the dispute over the ROW between San José and Gilroy:
Officials with the railroad and the California High Speed Rail Authority confirmed that they have held discussions in hopes of resolving their differences, which if not settled soon could cost the rail authority $3 billion in federal stimulus aid and state bond money, delay construction in Northern California and leave in doubt the electrification of Caltrain....
"Our position continues to be the same as what we've said in the past," Union Pacific spokesman Tom Lange said from Omaha, Neb. "The high speeds of these trains is simply not compatible in our right of way.
"We've had discussions with them, but the bottom line is that safety comes first and foremost."
There's been a lot of discussion in the comments about whether running HSR trains on tracks near the UPRR tracks, but not in their ROW, would pose a safety hazard of any sort. Maybe it does, maybe it doesn't, but UPRR's position is clear, and with the recent ruling in Atherton v. CHSRA it's clear that the issue has to be revisited. So it is good to hear that UPRR and CHSRA are talking, but it is quite unclear what are the substance of the talks and whether or not there's any hope of forward momentum.
One problem is that the judge that issued the ruling in Atherton v. CHSRA, Michael Kenney, did not actually indicate what remedies the CHSRA must undertake to address the three specific problems with the EIR the judge found. Despite claims from Peninsula NIMBYs and HSR deniers like Richard Tolmach, the judge has not ruled that the entire EIR must be redone or that the judge found the choice of Pacheco Pass to connect the Bay Area to the Central Valley was flawed. And as Richards' article makes clear, time is of the essence:
Timing is critical — and that has some officials saying the railroad's stance is a negotiating ploy, partly because the line is lightly used. Currently, just 14 trains run each day between Gilroy and San Jose — six freight, six commuter and two Amtrak trains.
On Oct. 2, the rail authority plans to submit its application for federal stimulus money. It needs approval of those funds soon to meet Washington's requirement that construction be under way by 2012.
If the judge rules that the entire environmental study be revisited, "that could be the death knell for construction on the Peninsula," said high-speed board member Rod Diridon. "If it's a remedial action, we can deal with that."
The recent ruling may also delay Caltrain's long-range plans to expand commuter service by converting its diesel trains to electric. This would enable the agency to speed up service and run more trains more quickly. It is relying heavily on stimulus cash to bankroll the $785 million initiative, $516 million of which is still unfunded.
Some will surely quibble, as they have in recent comments, that this shows the flaws of Diridon's insistence on including the Peninsula corridor in the CHSRA application for federal HSR stimulus funds. Personally I think the CHSRA was right to be aggressive in pursuing these funds. But this does make clear that more than the old Altamont vs. Pacheco dispute is at stake here. Federal stimulus funds are necessary to get construction underway on the Peninsula - construction that, as Mike Scanlon pointed out Wednesday night, is vital to Caltrain's survival.
As I have repeatedly predicted, the parties to this lawsuit have decided it is acceptable to risk the future of passenger rail in the Bay Area - including the HSR project and the very existence of Caltrain - to pick a fight over what is a comparatively small matter. True supporters of HSR would have accepted the Pacheco choice, worked to ensure it was built properly and with respect to the environment, rather than use that choice to try and blow up the whole project.
Still, it is good to see that CHSRA and UPRR are trying to be sensible about this and are talking to each other about the matter. These discussions can take quite a long time - UPRR has been dragging its feet on selling the Davenport-Pajaro line to Santa Cruz County for over 5 years now.
Tough negotiations with freight companies are nothing new. Twenty years ago, it took more than two years of talks before Caltrain agreed to buy the San Jose-to-San Francisco tracks from Southern Pacific for $242.3 million. Talks between the Valley Transportation Authority and Union Pacific dragged on for four years before the VTA agreed in 2002 to pay $80 million to run the BART-to-San Jose extension down the UP corridor between Fremont and San Jose.
"We've negotiated with them on several acquisitions, and they are very difficult negotiators," VTA General Manager Michael Burns said. "They are a private company out to protect their interests.
"But I will be very surprised if at the end they don't reach an agreement."
This is why I believe a federal role is absolutely necessary to ensure these negotiations conclude quickly and fairly to all sides. Current federal law gives UPRR all the negotiating power, enabling a freight railroad whose operations often seem stuck in the middle of the 20th century to hold up the development of a modern 21st century passenger railroad network.
President Barack Obama has made high speed rail a key part of his administration's vision for America's future. But so far he seems to have emphasized HSR funding over the other key policy aspects of implementing HSR. Now I'm not going to complain that Obama wants to change 60 years of federal transportation policy and finally direct some real funds to HSR. And yet that's not going to be enough to ensure HSR happens.
While I recognize that it is not Obama's style to force or pressure anyone into doing anything, both the White House and the Congress - particularly California's two powerful US Senators - need to be examining ways to modernize US railroad policy and legislation. In particular they need to redress the balance of power between the freight railroads, which are essentially private contractors for the federal government and who owe their very existence to the federal government, and the state and local passenger rail systems that the federal government wishes to promote and expand.
The best way to accomplish this would be to have Senator Feinstein or Senator Boxer help mediate these conversations, potentially alongside the Secretary of Transportation or even Vice-President "Amtrak Joe" Biden. They can encourage UPRR and CHSRA to quickly come to an agreement that satisfies both sides, while letting UPRR know that if they do not come to a quick agreement, then perhaps it would be time to change federal law to help provide entities like CHSRA a more level playing field - starting with eliminating the obsolete ban on states using eminent domain on federally-chartered railroads.
That would require a greater level of leadership from California's federal representatives than we have yet seen on HSR. But it is now time for them to step up and prevent a signature project from falling into a morass.
Wednesday, August 26, 2009
Initial Ruling in Atherton v. CHSRA
As I wait here in Menlo Park for the HSR town hall to get underway, we have a ruling in the frivolous lawsuit Menlo Park, Atherton, and the PCL filed against the CHSRA. It's a mixed bag for everyone - the judge ruled that most of the Federal EIR on the Pacheco alignment was sound and that most of the petitioners' claims about it were "without merit."
But there were three specific points that the judge DID rule had merit:
1. EIR claim that vibration from tracks can be mitigated to a "less than significant level" is "not supported by substantial evidence"
2. EIR inadequately described land use impacts from HSR (though the judge did throw out the arguments that HSR would produce sprawl)
3. EIR needed to have been "recirculated" based on Union Pacific's refusal to share ROW in the San Jose-Gilroy corridor area.
See the ruling for yourself:
athertonvchsra
The outcome is that the "writ of mandate" the petitioners sought is granted. In practice this is likely to mean the EIR will have to be revisited to consider the three points above. Other points that the court rejected, including the argument that US-101 and I-280 needed to be considered, or that Altamont itself needs to be reconsidered, do not appear to be reopened by this ruling.
More as it develops.
Monday, August 17, 2009
Innovation Place
Clem has a excellent overview of the tunnel and urban development concepts offered by a group calling itself Innovation Place. You can see some of their award-winning presentation or read more about the plan at Palo Alto Online. Clem's explanation of their ideas:
The crown jewel of Innovation Place is a complete transformation of the University Avenue station area, as envisioned in the team's graphic above. High speed rail or not, this area of Palo Alto is in dire need of a redesign; today, access between three important zones of activity (the University Avenue shopping district, Stanford University, and the Stanford Shopping Center) is a circuitous and dysfunctional jumble that is both unpleasant and time consuming to navigate, whether by foot, bike, car or bus. Neighboring areas just a few hundred feet apart feel miles away from each other.
The remainder of the Innovation Place proposal consists of a 31-acre linear park adjoining Alma Street, featuring a bike and pedestrian path and reuniting the two halves of Palo Alto formerly separated by the train tracks. The additional cost of putting the tracks underground would be financed by selling $700 million worth of air rights for development.
Go over to Clem's blog to read the full details and see some very intriguing designs, along with Clem's thoughts on the concept's strengths and weaknesses.
Personally I think this is exactly the kind of work that Palo Alto residents ought to be producing. Rather than trying to say "no" to the HSR/Caltrain project, the thinkers behind Innovation Place have said "yes" to integrating it into their community. It would be wonderful if Menlo Park and Atherton chose to follow this model instead of wasting taxpayer money on a lawsuit that is doomed to fail.
As to the concept (which should not be described as a "proposal" at this point since it isn't at that level of specificity), I like it. There's the question of the possible roller-coaster effect of a high speed train entering a tunnel for Palo Alto only, and whether $700 million is enough to underground the route. It's also unclear whether Union Pacific will go along with this, as it would pretty much eliminate their ability to continue freight operations over that section of track (although they could theoretically revive the Dumbarton corridor and use the shared tracks along the rest of the HSR/Caltrain corridor north to SF). But this is absolutely something worth exploring.
Tuesday, August 11, 2009
Frivolous Lawsuits, Part 2
As was expected, Atherton resident Russell Peterson filed his lawsuit against Caltrain and the CHSRA today in San Mateo County Superior Court. The link includes a picture of the happy family filing the suit, taken by proud papa Morris Brown.
There is a good debate going on in the comments to recent post about whether Peterson has standing to file a lawsuit based on a contract between the Peninsula Corridor Joint Powers Board and the Union Pacific Railroad. Although I am not a lawyer, it seems that Peterson has an uphill battle ahead of him.
The conspicuous absence here is, of course, UP itself. It would be a sign of a major decline in power and in fortunes if one of the nation's largest railroads was reduced to letting some NIMBY sue on their behalf. UP would have no trouble going into court if they felt it necessary to protect their interests.
Instead, as Quentin Kopp claims, UP prefers to work with the passenger rail agencies:
Judge Quentin Kopp, a member of the rail authority's board, bristled at that suggestion.
"Mike Brady apparently worries about Union Pacific, which itself manifestly refuses to join in his frivolous suit," Judge Kopp said. "To the contrary, Union Pacific representatives have in the last 30 days met with an authority member and the governor, as well as authority staff, on the subject of right of way use."
In response to a request for an interview, Caltrain said in a statement that "nothing has been done that would violate" Union Pacific's rights.
Now, Kopp's quote is vague, and he doesn't indicate what the content or the outcome of those meetings have been. But it is telling that UP doesn't see a need to go to court. Peterson is making one hell of a longshot bid here, a desperate attempt to try and stop the HSR project dead in its tracks.
The Almanac article doesn't report Clem's insight that the Caltrain/UP agreement language seems to indicate Caltrain, not UP, holds the cards here. But that seems par for the course for the Almanac, which has never really indicated to its readers that there is significant support for HSR in the area, or that the NIMBY claims rest on very weak ground.
The Almanac does speculate about how a tunnel might actually work to UP's advantage:
On the issue that looms largest in the minds of locals — whether the rail system would run underground, or on a berm — Peninsula residents and Union Pacific might find some common ground, Mr. Brady said.
For instance, running Caltrain and high-speed rail tracks through an underground tunnel, with Union Pacific freight running above ground, could be a win-win for both locals and the railroad giant, he said. Union Pacific wouldn't have to share the above-ground tracks, enabling it to run freight trains during the day. And Peninsula cities wouldn't have to confront a 15-foot-high berm bisecting their communities.
Perhaps Union Pacific would make the tunnel option, thought in many quarters to be prohibitively expensive, a condition for its consent to the high-speed rail system.
I would be very skeptical of this. If a tunnel is built, then there will be enormous pressure put on UP by the local governments to stop the freight hauling. The at-grade tracks will become seen as an anachronistic eyesore and the cities will salivate over the possibility of developing that land, given its prime location on the Peninsula. Tunnel proposals in several cities, such as Palo Alto, rely on selling the air rights over a tunnel to developers in order to help pay for the tunnel.
Surely Union Pacific knows this, and that is one reason why they have preferred to confer with the CHSRA and Caltrain on an above-grade solution that would preserve freight trains for quite some time along the Peninsula corridor. Peterson and his pals can try and use UP for their own purposes, but it seems clear to me that this frivolous lawsuit is going to fall on its face even more quickly than the Menlo Park/Atherton/PCL/Tolmach suit over Pacheco.
Saturday, August 8, 2009
Another Peninsula NIMBY Lawsuit
Clem has the scoop over on his blog about a planned lawsuit from an Atherton resident opposed to HSR that argues Union Pacific's consent must be given before the HSR project can proceed. From a Palo Alto Daily Post article:
Atherton resident Russell Peterson said yesterday he will file a lawsuit that will attempt to stop the state High Speed Rail Authority from starting any construction without the full approval of the Union Pacific Railroad....
Attorney Mike Brady, a Menlo Park resident representing Peterson, said the suit will ask a judge to require all plans for the bullet train to receive Union Pacific approval before construction begins.
As Clem lays out, this stems from Section 2.7 of the agreement between Caltrain and the UPRR, which seems to indicate that UP has to give its consent before any intercity trains can use the tracks. It is this clause that Peterson is using as the basis of his suit. I would be surprised if a judge finds Peterson has standing to sue using this agreement as a basis - wouldn't that be UP's place to decide whether or not to uphold their contractual agreement?
But as Clem found, there are other parts of the agreement that suggest Caltrain actually holds the cards here:
8.3.(c) In the event that Owner demonstrates a reasonably certain need to commence construction on all or substantially all the length of the Joint Facilities (including User's Cahill/Lick Line) of a transportation system that is a significant change in the method of delivery of Commuter Service which would be incompatible with Freight Service on the Joint Facilities (other than User's Cahill/Lick Line), Owner may, at its sole cost and expense, file no sooner than nine months prior to the commencement of such construction for permission from the ICC to abandon the Freight Service over the portion of the Join Facilities (excluding User's Cahill/Lick Line) upon which the construction is to occur. User shall not object to or oppose such a filing; however, it shall be allowed to participate in the abandonment proceedings.
Clem's interpretation is that the Caltrain/HSR project qualifies under this provision, although both Caltrain and the CHSRA have preferred to work with UP instead of against them. And that makes sense to me.
Peterson's suit will probably not go anywhere, but it does raise the issue of UP, its trackage rights, and how this affects Peninsula HSR planning. As Rafael has pointed out on several occasions, the tunnel that Peninsula NIMBYs prefer for the Caltrain/HSR corridor would almost certainly prevent freight trains from continuing to use the route.
Although it is theoretically possible that a tunnel could be built south of Redwood City and the Dumbarton rail bridge rehabbed to allow the UP freight hauler to continue to use the tracks, no money has been identified for this option, nor has it been seriously discussed. It's also worth noting that this would do nothing to help the cities further up the Peninsula, like Burlingame and San Mateo, that have also been calling for a tunnel. (Of course, I am quite confident that if Atherton, Menlo Park and Palo Alto felt they could solve their own problems by screwing the other Peninsula cities, they would gladly do so.)
If UP wants to continue running freight along the route, they are best off with an above-grade solution, and one has to assume they are quite well aware of this. Caltrain and the CHSRA are designing the route with UP's needs in mind. So why would UP have any interest in suing? No wonder a Peninsula NIMBY has to go it alone.
Saturday, March 28, 2009
Union Pacific Speaks
Never let it be said that I don't give HSR deniers credit where it is due. Morris Brown has obtained a copy of a letter from Union Pacific to the California High Speed Rail Authority laying out their stance on HSR implementation between San Francisco and Gilroy. Their overall attitude is one of "we own the corridor, either through easements or outright ownership, and you're going to implement HSR according to our guidelines."
The SF-Gilroy corridor is broken up into three pieces:
1. SF to Santa Clara, owned outright by the Peninsula Corridor Joint Powers Board (PCBJPB - set up in 1991 to run Caltrain) but where UP has an easement to run freight
2. Santa Clara to Lick, "a point approximately three miles south of Diridon Station" - UP "owns and has primary operating rights on Main Track Number 1".
3. Lick to Gilroy (and ultimately to Moorpark in Ventura County), owned wholly by the Union Pacific Railroad.
UP's stance as laid out in the letter is, in essence and going in reverse order:
3: No way in hell will HSR trains use the UP ROW between Lick and Gilroy. Their specific language is:
Union Pacific has no intention of allowing or permitting the Authority to build or operate the HSR within Union Pacific's right of way southward of Lick. The Authority should take this into account as part of the EIR/EIS for the San Francisco — San Jose segment.
2: Depending on how freight trains are mitigated, UP is fine with HSR between Santa Clara and Lick - but UP will be the final arbiter of what this means. Their specific language is:
The Authority must not undertake any action that interferes with Union Pacific's ownership and operation of Main Track No. I without prior approval from Union Pacific and the commuter agencies identified above. All adverse impacts must be mitigated to Union Pacific's satisfaction.
1: UP expects to not only maintain, but potentially increase, freight service along the Caltrain corridor, insists that its easement be respected, and that HSR be built to not adversely affect freight operations in any possible form.
Specifically, UP demands the following, which is most directly applicable to the Caltrain corridor:
(i) Slow speed freight trains and high-speed trains are incompatible on the same
tracks at any time, including cross-overs. Union Pacific requires overhead clearance of 23 feet 6 inches, which is higher than the Authority contemplates for its electrical system. The Authority must provide grade-separated cross-overs for freight trains at necessary locations. The Authority must not contemplate operation of freight trains on any HSR trackage at any time (and vice-versa). If necessary, completely separate freight trackage must be provided. HSR must comply with all applicable FRA regulations.
As far as I can tell what UP is saying is that at least one track has to be set up for freight trains, and if that requires a totally separate track, so be it - CHSRA and PCJPB are UP's bitch when it comes to making changes on the Caltrain corridor.
What does this mean for the battle over HSR implementation on the Peninsula? Brandon in San Diego lays it out like this:
any proposal to retain freight's ability with any necessary tunneling having the intent to accomodate HSR + Caltrain at the expense of an above ground alignment accomodating freight...
...will mean:
1) more costly tunneling efforts (bigger/higher, longer due to softer grade changes, and/or... ventilation) or
2) the tunneling to accomodate Caltrain + freight cannot happen at all.
If so on #2, that means Caltrain may remain above ground and possibly at-grade where they already are... and our friendly peninsula bergs are SOL.
I think that's a pretty good summation. Ultimately I think this deals a pretty significant blow to the tunnel concept as being floated by the Peninsula cities, who have floated a concept of a two-track tunnel. Unless the tunnel has four tracks and is large enough to accommodate UP freight, it's not going to meet UP's standards. Another option is to build a two-track tunnel and let UP continue operating freight trains on the surface above the tunnel, which is an absurd solution and also makes it impossible for cities to sell "air rights" to develop land above the tunnel to pay for the tunnel's costs, as some have proposed.
The only other option for Peninsula cities would be to pursue federal law that would limit UP's negotiating power. UP notes that their freight operations in this region are regulated by the federal Surface Transportation Board. Congress and the White House could, if they wanted to, pursue new laws and regulations pushing or even forcing freight railroads to accommodate HSR and other passenger rail even if they're reluctant to do so.
I am not sure we should expect that to happen. President Obama has shown hardly any desire to piss off large corporations like UP, and Congress has shown little interest in modernizing railroad law. If the federal government is serious about implementing HSR, they're going to need to attend to both, and the dispute over the Caltrain corridor may be a good place to start. But I am not confident it will actually happen.
Tuesday, March 10, 2009
LA - San Diego: Quo Vadis?
Note: commenter calwatch, a member of the Technical Working Group for the LA - San Diego segment of HSR, kindly contributed to the research for this post.
We recently discussed plans to completely remodel the overburdened Lindbergh Field airport and before that, the possibility of extending HSR to Mexico, because the SD Trolley Blue Line to the border is so busy.
Of course, both of these presumed that the planned HSR spur from LA Union Station to San Diego Santa Fe depot - or perhaps, a new multimodal transit hub at Lindbergh Field - will actually be built as intended. This requires that the starter line attract enough ridership to generate an operating profit that will permit the sale of non-state bonds to raise capital for phase II, which also includes extensions to Irvine and Sacramento. It also requires that CHSRA secure a suitable right of way, which will not be easy and needs to be done now, more than a decade before phase II construction will even begin.
Here is a map showing the principal railroad rights of way in Southern California (and their owners) plus several of the currently unused freeway medians. Despite appearances to the contrary, it does not represent a smorgasbord of options for HSR - the majority of them are already reserved for freight (expansion) and local/regional transit. At least the risky maglev project through the Inland Empire appears to have shrunk to just a gleam in a number of politicians' eyes: Sen. Harry Reid, Gov. Schwarzenegger and Gov. Gibbons. Rapid transit service between Anaheim ARTIC and Ontario airport via hwy 57 might be more easily implemented via a sexy bus styled by an F1 aerodynamicist and running at elevated speeds (90-150mph) on dedicated lanes and possibly even batteries. HSR is great, but it's not always the most appropriate option.
View Larger Map
Passenger rail service between LA and San Diego is currently provided by the popular Amtrak Pacific Surfliner that runs through Orange County and down the San Diego county coast. The trip takes about 2 hours.
HSR would cut that to 1h 15m, even though CHSRA has selected a preferred route via Riverside county that adds around 30 miles. There were three reasons for this preference:
- LAWA desperately wants to relieve California's largest airport LAX, where a project to add a third runway had to be canceled after protests from nearby communities. That is the primary reason why the HSR network includes both Palmdale and Ontario airports.
- San Bernardino, Riverside and other inland towns are currently only connected to LA via Metrolink, if at all. However, none of lines has a stop next to the airport terminals, the nearest large airport in the region.
- An HSR alignment along the coast ROW was ruled out because that is too narrow to support four tracks south of Fullerton in Orange County, because of the visual clutter an overhead catenary system would bring to San Clemente and Del Mar in particular and, because of concerns about weather-related and geological hazards that NCTD has had to deal with in the past. CHSRA recommended an upgrade to 110mph diesel-based service be considered but did not pursue the corridor any further.
The preference for a detour past Ontario airport and Riverside introduces several critical ROW issues:
- CHSRA is proposing expensive run-through tracks (zoom in on LA please) for a new upper deck at LA Union Station. We have already discussed several alternatives that would require fewer eminent domain takings on this blog. For a variety of reasons, most commenters insisted that HSR trains should stop at Union Station, not at any separate station connected by a local shuttle service - especially one anywhere near the new State Historical Park. Any run-through tracks for HSR would be separate from the ones already planned for FRA-compliant Amtrak/Metrolink equipment on the lower deck. The objective is to secure alignments that allow trains to run from SF/Sacramento to both Anaheim and San Diego without having to waste time reversing direction in LA. Note that there are no plans for direct HSR service between Anaheim and San Diego because Amtrak Pacific Surfliner already serves that market.
- Securing a ROW from LA Union Station to Riverside
- Securing a ROW from Riverside to San Diego
- Avoiding ROW conflicts with freight capacity expansion in Southern California. Fortunately, analysis to date suggests that a combination of expanding conventional rail freight and adding dedicated truck lanes on selected freeways would be a lot more more effective than an inland port served by a bleeding-edge electricity-guzzling freight maglev system in dealing with congestion and even air quality problems that are constraining growth in shipping volume.
This last point is really important, because 1 in 7 jobs in LA county depends on the ports. The majority of all manufactured goods imported from Asia into the US flows through the container terminals there and to point east via the Inland Empire. Already, rail freight up to Redondo Junction near downtown Los Angeles has been consolidated via the fully grade separated Alameda Corridor, freeing up old rights of way for projects such as the Harbor Subdivision Transit Corridor.
The success of freight consolidation has spawned a sequel dubbed Alameda Corridor East, with phase I already in progress. Its scope are improvements to 39 grade crossings the UPRR rights of way in the San Gabriel Valley between Redondo Junction and Pomona. The grade separation projects already completed did not anticipate the construction of HSR tracks, something CHSRA's consultant engineers HNTB (also selected for the SF peninsula) are aware of. Later phases will address the eastern section of the UPRR corridors out to Colton and beyond as well as the "91" corridor owned by BNSF, which CHSRA has identified as the preferred corridor between Redondo Junction to Fullerton. South to Anaheim and Irvine, the ROW is narrow and owned by Metrolink.
San Gabriel Valley
At this point, it looks increasingly unlikely that CHSRA can obtain land on the preferred UPRR Colton/Riverside and Colton ROWs for the purpose of constructing HSR tracks. The ROW choice is very much in flux, but right now leading candidates for alternatives out to Riverside appear to be, in no particular order:
- I-10 median on an elevated alignment. The section between LA Union Station and El Monte is already occupied by a single track used by the Metrolink San Bernardino line. The most likely route would therefore involve air rights over UPRR's Colton/Riverside ROW between Redondo Junction and the I-605/hwy 60 interchange, then cutting up to I-10 alongside I-605. The all-essential connecting transit to cover the ~1/2 mile to the three Ontario airport terminals would likely be implemented either via shuttle buses or an elevated people mover.
One big problem is that there is no easy way to cut across from Colton to the I-215 median, the preferred route down to San Diego. Colton, San Bernardino and Riverside all very much want a station in the area, but residents near March AFB in Moreno Valley are objecting. Note that Metrolink has plans for a new service out to Perris, Hemet and San Jacinto.
An alternative would be to cut across to the I-15 median just east of Ontario instead, perhaps even via the long-term parking lot at Ontario, S Haven Ave and a short section of UPRR's Colton/Riverside ROW (e.g. via air rights). The alignment would then continue south to Murrieta via Corona and Lake Elsinore. An intermodal station with Metrolink might be possible if the existing one for Corona were moved about a mile east. - Hwy 60 median east of the 710 interchange. It is still unused all the way out to Riverside UC and connected to the preferred route down to San Diego via the I-215 median. Reaching it from Redondo Junction would be difficult if UPRR refuses to cede at least air rights on its Colton/Riverside ROW . Moreover, there are two competing applications for the hwy 60 median: the Eastside Light Rail project and, dedicated truck lanes to haul freight out of the LA/LB ports (though other freeways are also under consideration).
For HSR, a bigger issue with this option is that hwy 60 runs a couple of miles south of Ontario airport. However, a sufficiently fast high-capacity shuttle bus service or people mover up S New Haven could link the HSR station, the East Ontario Metrolink station, the long-term parking lots and all three terminals. A suboptimal solution, but better than nothing.
Both the I-15 and the I-215 medians are more easily reached via hwy 60 than via I-10.
Note that both solutions involve obtaining some co-operation, e.g. air rights, from UPRR to proceed south-east from Redondo Junction. The same safety/liability issues that railroad raised in the context of a serious derailment with debris fouling an adjacent HSR track also applies to air rights. What if a derailment were to damage a support column or portal? How would the accident be communicated fast enough to avoid a potentially catastrophic follow-on accident involving a high speed train with hundreds of people on board?
Earthquake safety may be more manageable, though land would be needed to install the support structures. That could prevent UPRR from laying down another track and/or jeopardize the safety of its employees hanging off railroad cars. UPRR may be a crufty old-fashioned railroad compared to BNSF, but they are profitable and they have been in operation for 146 years. They've almost certainly forgotten more about day-to-day railroad operations and off-design conditions than CHSRA's board members will ever know.
HSR isn't being built in a vacuum, it is being introduced into the pre-existing US railroad ecosystem (for lack of a better term). If it has not yet done so, CHSRA would be wise to retain the services of a recently retired senior railroad operations manager, because neither civil engineers like Mehdi Morshed nor foreign HSR vendors nor foreign HSR operators will be able to bring local knowledge of (antiquated) operating practices to bear in CHSRA's negotiations with the freight rail companies and FRA. You can't reach consensus until the other side is persuaded that you fully understand the concerns they are raising. Operations guys tend to trust their own, because nothing focuses the mind on safety like an injury or death on your watch.
I-15 Managed Lanes
Unfortunately, getting past Ontario is only half the battle. SANDAG is already constructing additional managed lanes in the I-15 median that CHSRA was counting on in the 20-mile stretch between Escondido and south of Miramar. This video animation shows how this "freeway within a freeway" will be accessed via high overpasses. To date, no provision has been made to accommodate HSR. One option now under consideration would use even taller overpasses to permit tracks running on an aerial alignment.
A third option would rely on a covered trench below the center lanes, supported by columns in the middle. If this visually and mechanically more appealing variation is chosen, it would be prudent to anticipate those future trenches now rather than destroy nearly 40 lane-miles of perfectly good freeway lanes later on. One option would be to deploy prefabricated concrete slabs that could be removed during and re-installed after HSR construction. Another option would be to bite the bullet now and construct those trenches sans tracks in anticipation of HSR construction a decade hence. Worst case, HSR does not happen and they would be re-purposed for some other transportation application (zero emissions lanes? water pipes?) The question is: who would pay for digging trenches now rather than later? Note that the spaces between the on- and off-ramps would serve as emergency access points every few miles, eliminating the need for a service tunnel. The Escondido station should probably be sited north of where the managed lanes begin.
Note also that might be possible to obtain land just west of I-15 to avoid having to deal with the managed lanes complication, but 20 miles is a long stretch.
Miramar, Lindbergh Field and beyond
Further south, yet more pitfalls await our intrepid HSR planners. There is as yet no easy solution for cutting over from the I-15 median to the existing railroad coast ROW owned by the San Diego Northern Railway. The closest approach is at Miramar, a Marine Air Corps Station. County voters rejected a proposal to ask the Marines to leave so the field could be converted to a new airport far from downtown.
That ROW is wide enough for four tracks near Lindbergh Field, of which two are already in use for FRA-compliant equipment operated by Amtrak, NCTD and BNSF. The other two are used by SD Trolley, i.e. light rail. Unless FRA grants a rapid rail waiver along the same lines as the one that will be needed in Orange County, the HSR tracks will most likely have to run on an aerial, see slide 22 of this presentation. It seems highly unlikely that this would introduce any clearance problems for aircraft if wind conditions force them to take off to the east or, that wake turbulence and jet exhausts would even be noticeable to HSR trains. However, the authors appear to have include HSR at the last minute as an afterthought: there is no 400m (1/4 mile) island platform for the HSR trains nor any pedestrian overpass to reach them - three would be needed. Fixing this at a later date would require a massive change to the transit terminal's signature wave roof, so it should be elevated some 25-30' before the architectural plans are finalized.
Otherwise, CHSRA will have to stick with plan A and somehow site its station at the beautiful historic Santa Fe Depot near downtown or else further south, e.g. near Petco Park.
View Larger Map">
Finally, HSR will need a yard for overnight train storage, perhaps even maintenance. If BNSF are amenable to the idea, one possible location would be all the way down in near the salt ponds near Main St/I-5 in Castle Park. That location would double as an HSR station for communities near the border.
View Larger Map
